Engineering procurement and construction contract
Engineering, procurement, and construction (EPC) contracts, sometimes called turnkey contracts are similar to design and build contracts, in that there is a single contract for the design and construction of the project, but generally with an EPC contract, the client has less say over the design of the project and the contractor takes more risk.
On a design and build project, the client may produce an outline design upon which tenders are sought. On an EPC project, the client may seek tenders based on a performance specification and then have no input into the design, other than if variations are instructed.
Payment can be on a lump sum, cost reimbursable basis, or some other basis, but generally the client would be likely to seek a fixed price, lump sum agreement where the responsibility for cost control is taken by the contractor. This gives the client a relatively risk-free arrangement, with one point of responsibility and cost certainty. They can therefore operate the contract with the minimum resource.
The clients main risk lies in the definition of the specification upon which the contract is based. If the specification is not well developed and concise otherwise the quality and performance of the completed development may be compromised (see performance specification and output-based specification for more information)
Generally, EPC contracts are used on engineering and infrastructure projects, or industrial projects, where the aesthetics of design might be considered less important to the client than performance and cost certainty.
The FIDIC Conditions of Contract for EPC Turnkey Projects (The Silver Book) is an example of an engineering procurement and construction contract.
[edit] Related articles on Designing Buildings
- Construction contract.
- Contract conditions.
- EPCM contract.
- FIDIC.
- Output-based specification.
- Performance specification.
- Procurement route.
- Procurement team.
- Reliance data in EPC contracts.
- What is an EPC contract?
[edit] External references
- Skills Funding Agency: Procurement routes.
- CABE: Procurement routes.
- PACE Guidance on the Appointment of Contractors and Consultants for a detailed analysis of the pros and cons of various procurement routes.
- nbs: National Construction Contracts and Law Survey 2012.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.